Final update

Sunday 6th May 2012

The show barn is now a blank canvas ready for a range of contemporary furniture and accessories to come in from Dwell.

More Information

If you would like more information on building a Potton barn, why not request a Potton Contemporary brochure?

October 2011 Archive

First Fix

Monday 3rd October 2011

This month we have focused on getting the ‘first fix’ work completed, which essentially means getting the building to the stage where we put the plaster board on the internal walls. As such, we have had as many as six different trades working on the house at the same time; Manor Roofing and Timber Construction have been doing the roofing and cladding outside the house, while EBS, Proheat, Allergy Plus and Thinking Bricks have worked on getting ‘first fix’, electrics, plumbing work completed on the inside.